4/21/19 - 6/1/20

Iversen Center for Faith addition to St. Thomas Aquinas chapel.

Week of 10/28/19:

  • Continue foundation walls on Northwest wing and begin footings on Northeast wing.
  • Pour slab on grade (SOG) for Northwest wing.
  • Strip sky-deck system from South wing roof slab.
  • Install storm sewer line and underground mechanical, electrical and plumbing (MEP) rough-ins on North wing.
  • Piping, duct and electrical conduit install in utility tunnels ongoing.

Week of 11/4/19:

  • Form and pour footings, foundation walls and columns on Northeast wing.
  • Begin building sky-deck for Northwest wing.
  • Continue installing storm sewer and underground plumbing.
  • Piping, duct and electrical conduit install in utility tunnels ongoing.

ICF Progress Report - May 2019

ICF Progress Report - April 2019

5/29/19 - 8/14/20

Demolition of John Paul II (JP2) and construction of new dorm.

Week of 10/28/19:

  • Level 1 post-tensioned (PT) deck, pours 4 and 5.
  • Strip decking from level 1, pour 4, and finish installing decking for remaining level 1 pours.
  • Begin installing decking for level 2, pour 2.
  • Continue building and setting tables for level 2 decks.
  • Backfill around level 1, pour 5, and begin removing earth retention system.
  • Finish level 1 mechanical, electrical and plumbing (MEP) rough-ins and begin rough-ins on level 2.

Week of 11/4/19:

  • Level 1 PT deck, pours 6 and 7; level 2 PT deck, pours 1 and 2.
  • Strip decking from level 1, pours 5 and 6, and finish installing decking for level 2, pour 2.
  • Finish building tables for level 2 decks.
  • Continue pulling earth retention system along North foundation wall.
  • MEP rough-ins for level 2 ongoing.

FYH Progress Report - September 2019

FYH Progress Report - August 2019

FYH Progress Report - July 2019

FYH Progress Report - June 2019

5/28/19 - 7/17/20

Demolition of Faculty Residence and construction of new dorm.

Sidewalk on West side of Cleveland Ave, between Summit and Ashland Aves., will remain closed until Sept. 20th.

Week of 10/20/19:

  • Level 2 post-tensioned deck continues to be formed.
  • West side of level two will be poured this week.
  • Mechanical, electrical and plumbing (MEP) underground for the slab-on-grade (SOG) apartments are nearing completion.

Week of 10/27/19:

  • East side of level two will be poured this week.
  • Complete work on MEP underground for SOG apartments.

2YH Progress Report - Mid-October

2YH Progress Report - September 2019

2YH Progress Report - Mid-September

2YH Progress Report - August 2019

2YH Progress Report - Mid-August

2YH Progress Report - July 2019

2YH Progress Report - Mid-July

2YH Progress Report - June 2019

6/10/19 - 11/15/19

Conversion of former Child Development Center (CDC) to the new Center for Well-Being.

Update of work through end of August:

  • Framing on levels 1 and 2 have been completed.
  • Drywall has been hung following the rough-in of the "in-wall" electrical components and plywood backing
  • Taping, mudding and sanding of the drywall has begun to prepare the walls for paint.
  • HVAC, plumbing and electrical in-wall rough-in and the associated inspections have been completed.
  • Overhead plumbing lines, HVAC and electrical work has begun.
  • Hangers from the overhead concrete have started to be installed to prepare for the install of the chilled beams that will heat and cool the space.

Work during September:

  • Pain walls on levels 1 and 2.
  • Install chilled beams in 1 and 2.
  • Install ceiling grid for levels 1 and 2.
  • Install millwork (woodwork) on levels 1 and 2.
  • Install tile for restrooms on levels 1 and 2.

1/2/20 - 1/30/20

Installation of the elevator car.