4/21/19 - 6/1/20

Week of 1/6/20:

  • Continue stripping North post-tensioned (PT) deck formwork and shoring.
  • Install perimeter curbs and walls on North PT deck.
  • Mechanical, electrical and plumbing (MEP) rough-ins in utility tunnel and mechanical rooms ongoing.
  • MEP rough-ins in South half of building and MHC pedestrian tunnel.
  • Frame and glass install on West face (South half).
  • Enclosure process beins on West face of North half of building.
  • Precast install begins along East side of building (South half) and West side of building (North half).
  • Finish Hydrotech waterproofing of entire South PT deck.
  • Finish elevator shaft prep work prior to elevator installation.
  • Finish MHC to ICF tie-in/patch work (all except terrazzo patching).
  • Vinyl base quarter round installation in Chapel.

Week of 1/13/20:

  • Finish stripping North PT deck formwork and shoring.
  • Precast install continue along East side of building (South half) and West side of building (North half).
  • MEP rough-ins in utility tunnel and mechanical rooms ongoing.
  • Finish frame and glass install on West face (South half).
  • Sheetrock begins in South half of building.
  • Transportation of sand across North PT deck into West side of project side.
  • Installation of foam/sand on South PT deck.
  • Elevator installation in Chapel.

 

Iversen Center for Faith addition to St. Thomas Aquinas chapel.

 

ICF Progress Report - January 2020

ICF Progress Report - May 2019

ICF Progress Report - April 2019

5/29/19 - 8/14/20

Demolition of John Paul II (JP2) and construction of new dorm.

Week of 4/27/20:

  • Continue brick installation on Northern and Southeastern elevations.
  • Finish joisting and decking of dining area.
  • Continue installation of storefront and curtainwall windows.
  • Continue installation of light fixtures and electrical devices in dorm rooms.
  • Continue various HVAC rough-ins.
  • Drywall remaining walls on Level 5; drywall remaining ceilings on Level 3.
  • Taping walls on Level 2 and 3; painting in the Southern wing of Level 5.
  • Waterproofing shower floors in Southern wing of Level 3.
  • Tile and grout bathroom walls in Southern wings of Levels 4 and 5.
  • Complete installation of Northern elevator.

Week of 5/4/20:

  • Continue brick installation on Northern elevation.
  • Continue installation of storefront and curtainwall windows.
  • Continue installation of light fixtures and electrical devices in dorm rooms.
  • Continue various HVAC rough-ins.
  • Drywall ceilings in remainder of Level 4.
  • Taping walls in remainder of Level 4; painting in the remainder of Level 2.
  • Waterproofing shower floors in Southern wing of Levels 2 and 3.
  • Tile and grout bathroom walls in Southern wing of Level 5.
  • Dismantling of tower crane begins.

FYH Progress Report - January 2020

FYH Progress Report - December 2019

FYH Progress Report - November 2019

FYH Progress Report - September 2019

FYH Progress Report - August 2019

FYH Progress Report - July 2019

FYH Progress Report - June 2019

5/28/19 - 7/17/20

Demolition of Faculty Residence and construction of new dorm.

Weeks of 3/23/20 and 3/30/20:

  • Punched windows are ongoing, completed through level 5.
  • Sunshade bracket installation is completed.
  • Brick, precast and stone installation is completed in the South and West corners; work continues on Southeast and North sides of building.
  • Stairwell S3 is erected; stairwell S2 is being erected this week.
  • Apartments have been painted and tile installation is ongoing.
  • Mechanical, electrical and plumbing (MEP) trade installation, interior light gauge framing and backing for walls are all ongoing.
  • Installation of 2-car passenger elevator is ongoing.
  • Level 2 fireplace installation is completed.

2YH Progress Report - January 2020

2YH Progress Report - November 2019

2YH Progress Report - Mid-October

2YH Progress Report - September 2019

2YH Progress Report - Mid-September

2YH Progress Report - August 2019

2YH Progress Report - Mid-August

2YH Progress Report - July 2019

2YH Progress Report - Mid-July

2YH Progress Report - June 2019