4/21/19 - 6/1/20

Iversen Center for Faith addition to St. Thomas Aquinas chapel.

Week of 9/9/19:

  • Form and pour foundation walls, columns and elevated tunnel slab.
  • Begin installing underground utilities, and mechanical, engineering and plumbing (MEP) rough-ins on South side of building.
  • Continue excavation for elevator pit and stair landing in North end of Chapel.
  • Waterproof and backfill foundation walls as needed.

Week of 9/16/19:

  • Form and pour foundation walls, columns and slab on grade.
  • Begin setting deck for first post-tensioning (PT) pour on South side of building.
  • Waterproof and backfill foundation walls as needed.
  • Continue underground MEP rough-ins, sleeving and piping install.

ICF Progress Report - May 2019

ICF Progress Report - April 2019

5/29/19 - 8/14/20

Demolition of John Paul II (JP2) and construction of new dorm.

Week of 9/9/19:

  • Finish footings, foundation walls and columns; slab on ground pours 2b and 3.
  • Begin setting deck for level 1, pour2; pour level 1, pour 1.
    • Partial lane closure on Selby Ave. on Sept. 13, for a few hours.
  • Waterproof and backfill foundation walls; grade for slab on grade pours.
  • Mechanical, electrical and plumbing (MEP) rough-ins below slab on grade and on level 1 deck.

Week of 9/16/19:

  • Finish any remaining foundation walls; slab on grade pour 4.
  • Finish setting deck for level 1, pour 2, and begin installing rebar and post-tensioned (PT) cables.
  • Waterproof and backfill remaining foundation walls; grade for slab on grade pour.
  • MEP rough-ins below slab on grade and on level 1 deck.

FYH Progress Report - July 2019

FYH Progress Report - June 2019

5/28/19 - 7/17/20

Demolition of Faculty Residence and construction of new dorm.

Sidewalk on West side of Cleveland Ave, between Summit and Ashland Aves., will remain closed until Sept. 20th.

Week of 9/8/19:

  • Slab-on-grade for parking level.
  • Begin decking for level 1.
  • Storm infiltration system installation has been pushed back and will go in the next few weeks.

Week of 9/15/19:

  • Continue decking for level 1.
  • Continue installation of storm infiltration system.

2YH Progress Report - August 2019

2YH Progress Report - Mid-August

2YH Progress Report - July 2019

2YH Progress Report - Mid-July

2YH Progress Report - June 2019

6/10/19 - 10/18/19

Conversion of former Child Development Center (CDC) to the new Center for Well-Being.

Update of work through end of August:

  • Framing on levels 1 and 2 have been completed.
  • Drywall has been hung following the rough-in of the "in-wall" electrical components and plywood backing
  • Taping, mudding and sanding of the drywall has begun to prepare the walls for paint.
  • HVAC, plumbing and electrical in-wall rough-in and the associated inspections have been completed.
  • Overhead plumbing lines, HVAC and electrical work has begun.
  • Hangers from the overhead concrete have started to be installed to prepare for the install of the chilled beams that will heat and cool the space.

Work during September:

  • Pain walls on levels 1 and 2.
  • Install chilled beams in 1 and 2.
  • Install ceiling grid for levels 1 and 2.
  • Install millwork (woodwork) on levels 1 and 2.
  • Install tile for restrooms on levels 1 and 2.

1/2/20 - 1/30/20

Installation of the elevator car.