4/21/19 - 6/1/20

Iversen Center for Faith addition to St. Thomas Aquinas chapel.

Week of 7/1/19:

  • Installation of storm water retention system along Cleveland Ave. continues.
  • Underpinning work on North end of Chapel continues.
  • Forming and placement of footings for North, South and East wings begins.
  • Construction of MHC tunnel, Ireland Hall tunnel, and mechanical rooms continues.
  • HVAC and electrical rough-in begins in the utility tunnel.

Week of 7/8/19:

  • Finish installation of storm water retention system along Cleveland Ave.
  • Complete construction of MHC and Ireland Hall tunnels and backfill.
  • Construction of mechanical rooms continues.
  • Continue underpinning at Chapel entry.

ICF Progress Report - May 2019

ICF Progress Report - April 2019

5/29/19 - 8/14/20

Demolition of John Paul II (JP2) and construction of new dorm.

Week of 7/1/19:

  • Forming and pouring of building footings continues.
  • Begin forming and placement of columns and foundation walls.
  • Finish demolition of JP2; excavate and demolish below-grade structure.
  • Earthwork and foundation excavation continues on South side of project.

Week of 7/8/19:

  • Continue forming and pouring footings.
  • Begin forming and pouring columns, walls and slab on grade.
  • Earthwork and foundation excavation continues on South side of project.
  • Installation of site utilities and underground plumbing begins.

FYH Progress Report - June 2019

5/28/19 - 7/17/20

Demolition of Faculty Residence and construction of new dorm.

Week of 7/14/19:

  • Continue mass excavation, and addition of footings and foundations.
  • Installation of tower crane pad.

Week of 7/21/19:

  • Continue addtion of footings and foundation walls.

2YH Progress Report - Mid-July

2YH Progress Report - June 2019

6/10/19 - 10/18/19

Conversion of former Child Development Center (CDC) to the new Center for Well-Being.

Week of 6/24/29:

  • Start demolition of 1st floor

Week of 7/1/19:

  • Complete demolition of 1st floor
  • Start demolition of 2nd floor
  • Selective demolition of basement
  • Saw cut floor and start underfloor plumbing
  • Layout of heating/cooling and electrical

5/27 - 9/1

Addition of an elevator shaft accessing lower level and 1st floors.

Addition of carpet in all cooridors on lower level and 1st floors.

Renovation of lower level restrooms.

 

1/2/20 - 1/30/20

Installation of the elevator car.