St. Paul Campus Projects
Estimated completion date: November 2023
Key Construction Activities - May 2023
- Exterior Enclosure
- Exterior framing and sheathing
- Stone installation
- Exterior metal panel installation
- Exterior glass installation
- Interiors
- Mechanical and electrical rough-in
- Interior framing
- Drywall installation
- Taping and painting
- Freight elevator installation
- Fire alarm, low voltage and AV installation
- OWS Work Related to Schoenecker Center
- Mechanical and electrical work
- Installation of roof piping
Project Updates with progress photos
- June 2022
- July 2022
- August 2022
- September 2022
- October 2022
- November 2022
- December 2022
- January 2023
- February 2023
- March 2023
- April 2023
- May 2023
Progress Photo from Grand Ave. 05/11/23
Progress Photo from Summit Ave. 05/11/23
Cistern assembly time lapse video - 09/29/22
Fuel oil tank time lapse video - 10/28/22
Video and notes by Chief Engineer, David Clysdale, 02/16/23
The Schoenecker Atrium Grand Staircase is starting to come together. The stairs are unique in that they are not supported from the bottom but suspended from the roof. There are four iron sections to each floor’s stairs - the landing, single wide stair section and two side curved stairs. Each floor’s landing will be shored up until the suspension rods are secured to the roof iron work and then the shoring will be removed.
Construction Management Plan_4-27-22
Phased Site Logistics Plans_4-27-22
Please click the link for more info:
https://tommiesports.com/feature/lee-and-penny-anderson-arena
Check back soon for construction updates.
Start date: Winter 2023
- Adding an additional emergency generator to add capacity to our existing systems
- Location will be in the Morrison Parking Ramp
- Design is complete and subcontractors are being hired
Start Date: February 2022
Estimated Completion Date: May 2023
- Saint John Vianney College Seminary begins their building expansion in February 2022.
- Most of the work will be located on the north side of the building near Tommie North.
- Zeman Construction is the contractor working directly with the SJV team.
- Lot A will be closed 2/21/22 until the end of the project.
- Based on Zeman's current staging plan, the sidewalk between SJV and Mennith Hall should remain open for the majority of the project.
- Link to more info on the project: https://sjvseminary.org/saint-john-vianney-college-seminary-building-project/
May 2023 Progress Photo
Estimated start date: Summer 2023
Parking Lot K Improvements
- Electric vehicle charging
- Bike parking options
- Landscape improvements
Estimated Start Date: Summer 2023