Timetable
Here is a timetable of anticipated activities. The schedule is subject to change, depending on weather conditions and progress made by crews. The university will update its campus construction web site every Friday from May until the project concludes.
- May 1: A construction fence is installed around the construction site.
- May 8-14: The site is excavated over five working days.
- May 15-29: Footings and foundations are poured over 10 working days.
- May 22-June 5: The elevator shaft is installed over 10 working days.
- June 1-July 7: The structure and exterior are constructed.
- July 7-13: The interior is roughed in.
- July 31-Aug. 20: Exterior brick is laid and roofing is installed.
- July 31-Oct. 9: The interior is completed.
- Sept. 1-15: The site is landscaped.
- Oct. 12-30: The building is furnished and equipped.
- Nov. 1: Faculty and staff move in.