Construction vehicles will use Cleveland and drive onto the property at its northwest corner (Cleveland and the alley). The staging area will include the backyard, the parking lane on the east side of Cleveland from a spot 25 feet north of Summit to the alley, and the equivalent of two parking spaces on the east side of Cleveland north of the alley. A chain-link fence will be installed to separate the staging area from the northbound Cleveland driving lane.
During the week of May 4, excavation crews will remove an estimated 60 truckloads (600 cubic yards) of soil, or an average of 12 loads per day. Trucks leaving the site will turn north on Cleveland to Marshall and west on Marshall to Cretin.