Construction crews will work from 7 a.m. to 4:30 p.m. on weekdays, although their schedules could be extended to 6 p.m. during the summer to take advantage of the weather.
Crews may work an occasional Saturday if necessary to stay on schedule, with shifts beginning at 8:30 a.m.
Ryan Companies expects 20-40 employees on the site during May and June. There will be more activity on the site, with 50-70 employees, in July, August, September, October and November. The numbers will drop to 20-40 employees in December and January.
Crew members will park in Lot T immediately north of McCarthy and in Lot O southwest of McCarthy until early November, when they will be able to park in the lower level of the ramp.