Timeline
Here is a timetable of anticipated activities. The schedule is subject to change, depending on weather conditions and progress made by crews. The university will update its campus construction web site every Friday from June 2009 until the project concludes in October 2010.
-
Mid-April-May 29: Demolition preparation occurs in Foley, Schoenecker and Coughlan, including asbestos abatement in Foley.
-
May 26: A construction fence is installed around the building and the staging area, which includes a portion of Lot H.
-
June 1: Demolition begins on Foley, Schoenecker and Coughlan, and could take three weeks.
-
June 22: Excavation begins for utility tunnels, foundations and water-retention pools.
-
July: Work begins on below-grade concrete footings and foundations.
-
Mid-July/August: Structural precast and structural steel erection begins.
-
September-March: The structure and exterior of the new complex are constructed.
-
March-September (2010): Interior and specialty work is completed.
-
October (2010): Athletic, faculty and staff members move into the new complex.