Construction crews will work from 7 a.m. to 4:30 p.m. on weekdays, although their schedules could be extended to 6 p.m. during the summer to take advantage of the weather. Crews may work an occasional Saturday if necessary to stay on schedule, with shifts beginning at 8:30 a.m.
Opus expects an average of 40-50 employees on the site during the summer 2009, with crew sizes slowly increasing and running as high as 100+ during the winter and spring of 2010. Crew members will park in Lot H.